    stats homework




    A car manufacturer takes an average of 17.5 hours to construct a car. This includes time for stamping, welding, painting, assembly and inspections. Construction times vary with a standard deviation of 30 minutes and these times follow a normal distribution

    b. What is the probability that a randomly selected car manufactured at this plant takes between 18 and 19 hours to construct?

    c. Find the probability that the construction time for a randomly selected car manufactured at this plant is less than 17 hours and 50 minutes.

    I dont think my working is correct for b. can someone help me out please

    crap my photos are terrible

    b is basically 1080-1050/30 to get a z-score of 1 which is 0.8413
    1140-1050/30 to get a z-score of 3 which is 9.9987
    Im not sure where to go from there
    Attached Images  

  2. #2
    Points: 4,841, Level: 44
    Level completed: 46%, Points required for next Level: 109
    Con-Tester's Avatar
    Posts
    167
    Thanks
    3
    Thanked 59 Times in 57 Posts

    Re: stats homework


    The answer to (b) is the area under the n(0, 1) curve between z = (18-17.5)/0.5 = 1 and z = (19-17.5)/0.5 = 3.

    The answer to (c) is the area under the n(0, 1) curve between z = –∞ and z = (17.8333-17.5)/0.5 = 0.6667.